CAO Rebecca Nabwami · Jinja DistrictScope · District · 168,400 households

24 Months · One Platform · Every Tier of Local Government

Delivery Roadmap

Uganda does not need another five-year ICT project. It needs a government operating system that delivers measurable results within 24 months.

Phases

8

Deliverables

43

Months

24

Est. budget

UGX 2.5–3.8B

Workstream
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
M13
M14
M15
M16
M17
M18
M19
M20
M21
M22
M23
M24

Phase 0 · Months 12

Program setup & design lock-in

Budget · UGX 120–180M

Governance, legal, pilot scope, workflow maps, baseline KPIs.

Key deliverables

  • Program charter
  • Pilot scope
  • Role/jurisdiction matrix
  • Workflow maps v1
  • Data model v1
  • Baseline KPIs

Owners

Programme Director · Product Lead · Legal · Architect

Dependencies

  • Pilot sponsor
  • Governance committee
  • Legal review

Exit gate

Pilot site approved · scope frozen · workflows agreed